The New Austrian Tunneling Method (NATM) embodies a pioneering philosophy that has revolutionized the world of tunnel construction. Developed in the late 1950s in Austria, the NATM approach represents a departure from traditional tunneling methods, emphasizing adaptability, geological observation, and an iterative design process.

The NATM approach to tunneling is based on the principle of supporting the tunnel face using a combination of rock mass and ground support elements, such as shotcrete (sprayed concrete), rock bolts, and steel arches, as excavation progresses. This method differs from traditional tunneling methods that require immediate full-scale support of the tunnel face with tunnel lining or supports.

Here are the key principles and applications of the NATM philosophy,

Preliminary Investigations:

Extensive geological and geotechnical surveys are conducted to gather data on the rock mass properties, groundwater conditions, fault zones, and other relevant factors.

Rock mass classification systems, such as the Q-system or RMR (Rock Mass Rating), are often used to assess the rock mass quality and stability.

Geological mapping, core drilling, geophysical surveys, and laboratory testing are performed to gather comprehensive data for the design phase.

Design Phase:

Based on the gathered data, an initial tunnel design is developed, considering factors such as the anticipated ground conditions, tunnel size, alignment, and structural requirements.

Numerical modeling techniques, such as finite element analysis or distinct element method, may be employed to simulate the behavior of the rock mass during excavation and to optimize support design.

Groundwater control measures, such as grouting or drainage systems, are designed to manage water inflows during excavation.

Excavation:

Tunnel excavation typically begins with a heading excavation at the tunnel face using conventional methods like drilling and blasting or mechanical excavation.

The NATM emphasizes controlled excavation in small sections (typically around 2-3 meters) to allow for close monitoring of the ground conditions and to mitigate potential risks.

The use of systematic benching or benching with invert construction is common, allowing for stable working conditions during excavation.

Initial Support:

Immediate support measures are implemented as soon as the tunnel face is excavated to provide temporary stability and protect workers.

Shotcrete (sprayed concrete) is applied to the exposed excavated surface immediately after excavation, acting as primary support.

Rock bolts are installed to reinforce the shotcrete and stabilize the surrounding rock mass.

Steel arches or other ground reinforcement elements are utilized as necessary to enhance the initial support system.

Monitoring and Instrumentation:

Monitoring instruments are strategically installed within the tunnel and surrounding rock mass to continuously monitor and assess the behavior of the excavation.

Instruments may include extensometers, convergence monitors, inclinometers, strain gauges, and piezometers to measure displacements, stresses, water pressures, and other parameters.

Monitoring data is analyzed to evaluate the stability of the tunnel and to make informed decisions regarding support adjustments or remedial measures.

Final Support and Lining:

Once a section of the tunnel is excavated, supported, and monitored, and the rock mass is deemed stable, a final lining is constructed.

The final lining may consist of concrete segments, cast-in-place concrete lining, or other suitable methods depending on the project requirements.

The lining provides long-term structural support, protects against water ingress, and may accommodate utilities or other functional elements.

Continuous Adaptation:

The NATM emphasizes flexibility and adaptability throughout the construction process.

Ground support measures are continuously adjusted based on the observed behavior of the rock mass, as revealed by monitoring data.

In case of unexpected geological conditions, the NATM allows for modifications to the tunnel alignment, shape, or support strategy to ensure safety and stability.

The New Austrian Tunneling Method (NATM) is a widely used approach for tunnel construction and design. While there is no specific international code or standard exclusively dedicated to NATM, several codes and guidelines provide relevant guidance for NATM tunnel design. Here are some of the key codes and standards commonly referenced in NATM tunnel design:

  • Eurocode 7: Eurocode 7, titled "Geotechnical design," provides principles and rules for geotechnical design, including the design of tunnels. It covers various aspects, such as soil and rock mechanics, ground investigation, stability analysis, and design approaches.
  • Swiss Tunneling Society (STS) Guidelines: The Swiss Tunneling Society (Schweizerischer Tunnelbauverein, STS) has developed comprehensive guidelines for tunnel design and construction. These guidelines, known as the "Guidelines for the Construction of Tunnels and Shafts," are widely used in NATM projects and provide detailed recommendations for geotechnical investigations, support design, monitoring, and construction procedures.
  • British Standards (BS): British Standards include several codes relevant to NATM tunnel design. For instance, BS 6164 provides recommendations for health and safety in tunneling works, while BS 8002 offers guidance on earth retaining structures and includes information applicable to NATM tunnels.
  • International Tunnelling Association (ITA) Guidelines: The International Tunnelling Association has produced several guidelines that encompass various tunneling methods, including NATM. While not specific to NATM, these guidelines offer valuable insights into general tunneling practices and principles, such as excavation stability, rock support, and instrumentation.
  • Austrian Standards (ÖNORM): Austria has been at the forefront of NATM development, and the country's standards (ÖNORM) offer valuable guidance for NATM tunnel design. ÖNORM B 2202-1 covers the design and construction of underground structures, including tunnels, and provides specifications for geotechnical investigations, rock support, and monitoring.
  • International Society for Rock Mechanics (ISRM) guidelines: The ISRM publishes several guidelines relevant to NATM tunnel design, such as "Suggested Methods for the Quantitative Description of Discontinuities in Rock Masses" and "Guidelines for Rock Support Testing."

Project-Specific Specifications: In addition to the above codes and standards, NATM tunnel design often incorporates project-specific specifications and requirements. These can be provided by the project owner, consulting engineers, or local authorities and may include design parameters, safety factors, construction methods, and monitoring plans.

In India, tunneling projects are generally designed and executed according to various codes and guidelines. Some of the key Indian codes and standards related to tunneling are:

Indian Road Congress (IRC) Codes: The Indian Road Congress has published several codes related to tunneling, including:

  • IRC:SP:87-2018 - "Guidelines for the Design and Construction of Tunnels and Subway Structures"
  • IRC:SP:89-2010 - "Guidelines for Design of Tunnels (Open Cut and Bored)"
  • IRC:SP:92-2010 - "Guidelines for the Design of Structural Measures for Slope Stability"
  • IRC:SP:105-2015 - "Guidelines for the Geotechnical Investigations for Highway Projects"

Indian Standards (IS): The Bureau of Indian Standards (BIS) has published various standards applicable to tunneling and geotechnical engineering. Some relevant IS codes include:

  • IS 14458:2018 - "Code of Practice for Design and Construction of Shaft and Gallery in Rocks"
  • IS 1904:1986 - "Code of Practice for Design and Construction of Foundations in Soils: General Requirements"
  • IS 5878:1970 - "Criteria for Design of Machine Foundations - Part 1: Foundation for Reciprocating Type Machines"
  • IS 7894:1975 - "Code of Practice for Design and Construction of Pile Foundations: Part 1 - Concrete Piles"

Central Public Works Department (CPWD) Specifications: The Central Public Works Department of India has its own specifications for civil engineering projects, including tunneling. CPWD specifications often serve as a reference for tunnel design and construction.

It's important to note that while these codes and standards provide guidance for tunneling projects in India, they may not be specifically tailored to the New Austrian Tunneling Method (NATM). However, the principles and requirements outlined in these codes can be adapted to suit the project requirements and specific ground conditions encountered during NATM tunneling projects.

It is always recommended to consult with experienced geotechnical engineers, tunneling experts, and relevant authorities to ensure compliance with the latest codes, standards, and guidelines for tunneling projects in India.